The team continued to review INFORM requests and prioritize various tickets and began to work on reducing some of the back-log. Beyond working on INFORM tickets and communicating various project status, the team also worked on many items including:
- Alma/Primo (Nancy, Jamen, Tao)
- Completed loading missing items
- Started configuration of Proquest EDI
- Continued to create/modify user roles as needed
- Digital Collections (Nathan, Judy, Scott)
- Continued to load ESSSS and Commodores to reduce back-log
- Reviewing display changes in Archives Space
- Scanned materials for Curator talk
- Web (Jodie and Matt)
- Continued to work on reported issues with areas of the new website
- Adjust some text on the TVNews website
- Worked on Google Tag Manager configuration
- Other items (All)
- Caught up on ETDs
- Met with Discover Garden to discuss audit process
- Re-image and replace several older computers
- Attended several meetings with others in the library and on campus.
- Began preparing for migrating the library SharePoint environment to the new version
- Started review of the Library Active Directory (AD) Organizational Unit (OU) in preparation for the new directory services (project Genesis)